EBARA Corporation (hereinafter "EBARA") is pleased to announce the completion of a new overhaul factory (hereinafter "Main Factory") for dry vacuum pumps, a flagship product of the Precision Machinery Company. With the completion of this factory, our company now has five dry vacuum pump overhaul factories in Japan.


1. Background


Our company entered the semiconductor-related field in the 1980s, applying our expertise in fluid technology and rotating machinery technology. The semiconductor market is predicted to reach 1 trillion dollars (approximately 150 trillion yen) in 2030, and demand for dry vacuum pumps, which are indispensable at semiconductor manufacturing sites, is also expanding. In order to expand our after-sales service, we started construction of this factory in December 2023, and the building has now been completed. It is scheduled to begin operation in April 2025.


2. Overview


In the process of processing wafers that will become semiconductor substrates, air is removed from the processing space called the chamber using a vacuum pump to create as high a vacuum as possible to prevent the introduction of impurities (such as gas molecules). The "dry vacuum pumps" we manufacture are designed without using oil in the gas-contacting parts, so there is no need to worry about contamination caused by backflow or diffusion of water or oil, and a clean vacuum can be obtained. At this factory, we check the condition of the dry vacuum pumps returned from the customer's factory, disassemble, clean, repair, replace parts, assemble, test, etc., to make them perform as well as new ones, and then deliver them back to the customer's factory.


3. Details of the new overhaul factory

 

NameEBARA FIELD TECHTohoku Factory
Location1-6 Kuwata, Hobara-cho, Date City, Fukushima Prefecture
Facility detailsOverhaul of dry vacuum pumps
AreaBuilding area: Approximately 3,000 m2
Site area: Approximately 10,000 m2
1 story above ground
Start of operation (planned)April 2025

This factory will also contribute to efforts to reduce the environmental impact through such measures as installing solar panels on the roof of the building and recycling production wastewater within the factory. Additionally, we will also work to improve employee engagement by installing three EV (electric vehicle) charging stations in the on-site parking lot for employee use and a Japanese-style room in the refreshment room.


4. Future Developments


With the construction of this new factory, we will support the stable operation of our customers' production activities and contribute to the further development of the semiconductor industry, which continues to diversify and accelerate, and to the "creation of an evolving and prosperous life" set out in our long-term vision, "E-Vision 2030."


- About the EBARA Group -

The EBARA Group will work to achieve the Sustainable Development Goals (SDGs) and further increase its corporate value by addressing key ESG issues based on its long-term vision and medium-term management plan.

※ EBARA FIELD TECH. CORPORATION: A group company of EBARA Corporation, which sells and provides after-sales services for component equipment and semiconductor manufacturing equipment.